Given Volkswagen’s corporate goal to maintain its highly competitive position for new production, it is important that its key performance indicators, such as low production costs, short throughput times, high quality and efficient production of model varieties, are met. Requirements for production and logistics processes include; discipline in supply chain deliveries, low inventory levels, low capital allocation and fulfilling the planned production program.
VOLKSWAGEN SLOVAKIA, a.s. was founded in 1991 and now employs more than 9000 people and produces more than 280,000 cars, 330,000 gearboxes and 17 million components a year. The company is based near Slovak’s capital, Bratislava.
As growth continued at the plant, the Industrial Engineering Department of VW SLOVAKIA a.s. undertook several simulation projects aimed at optimising the new production and logistics systems using WITNESS, including:
One of the two projects involved a simulation of a complex automated guided vehicle and load carrier system for material supply of the VW Touareg assembly line. The goal of the project was to analyse the planned system and evaluate the following:
Simulation analysis identified a bottleneck in the AGV charging times and AGV speeds in manufacturing line replenishment zones.
Simulation experiments showed that with optimal settings of charging stations parameters and AGV speeds in system zones, it is possible to operate the system with 10% less than the originally planned number of automated guided vehicles.
After the commissioning of the whole production system, the simulation project results have been verified in real life. Simulation also showed that the initial AGV positions at the beginning of the production week, originally planned based on the static analysis, needed to be changed.