Contact Twinn

CONTACTER Twinn

Nissan uses WITNESS simulation solution from the Lanner Group to achieve the production of three separate high-volume models on two assembly lines at its plant in Sunderland


Background

Nissan initially used WITNESS, widely regarded as the world’s leading process simulation tool, to establish the plant’s capability to achieve production targets and to identify where improvements were needed to sustain the required productivity. WITNESS was also used to calculate and validate the most efficient sequence in which the different models should pass through various stages in the assembly process, and to identify ‘hot spots’ where any problems would rapidly impact on volume throughput.

By the close of the 1990s Nissan Sunderland plant, Europe’s most productive car factory, was producing the Primera and Micra models on two separate assembly lines. When the Almera mid-range hatchback was launched in 2000 it was decided, to minimise capital expenditure, to integrate its production into the existing two-model plant configuration rather than add a third assembly line. The Almera had to be introduced without disrupting existing production.

Initial engineering evaluations indicated that it was feasible to produce three models on two lines, but Nissan then needed to examine in fine detail how each model should be sequenced through the various stages of production. 

“This was such a complex task that it was impossible to do manually,” explains Paul Wreglesworth, Nissan’s Production Controller. “Creating a computer model to simulate the processes was the best solution, and with its proven track record in the manufacturing industry, particularly in the automotive sector, Lanner’s WITNESS was the obvious choice.”

Working closely with the engineers Paul Wreglesworth’s team created separate WITNESS models for the main line and sub-assembly facilities - the Body Shop, Paint Shop and Trim Shop - on both the existing production lines. The fundamental premise was that the Primera and new Almera models would move down separate lines; the Micra would share the Almera line but with the vital capability of being switched between both lines.

The WITNESS models were not concerned with achieving target volumes. What was critical, however, was establishing efficient new body build sequencing to accommodate all three models (and their numerous variants) and identifying and eliminating potential bottlenecks.

Issues

Nissan identified three clear sets of issues which would have to be addressed when developing the WITNESS models. Firstly Nissan determined which elements of the assembly process would need to be modelled, and to what level of detail. Three distinct areas were identified: the main-line and sub-assembly facilities, and the ‘buffering’ arrangements. ‘Real life’ data on cycle times within these processes was supplied by the Engineering department and validated by the Production department. Then the ‘inter-elemental’ logic had to be specified - body movements in the Body Shop, sequencing in the Paint Shop and the prioritisation protocols in the buffer storage areas.

Secondly Nissan had to examine the proposed weekly working patterns to accommodate the three models, taking into account strip-out operations. The question of breakdowns also had to be addressed, initially using actual data gathered from the existing Primera and Micra assembly operations and then developing predictive breakdown profiles taking into account the integration of the new Almera assembly. “We also had to identify a number of variable that would be needed in the WITNESS model,” explains Paul Wreglesworth. “Variables in operation, for logical decisions and for the required output of the three model types.”

Thirdly, and lastly, Nissan turned its attention to creating input schedules, first done manually and then system-generated, which in turn led to the development of work in progress (WIP) schedules. 

“By the time we arrived at this stage we had a clear understanding of the output data required of the WITNESS model,” says Paul Wreglesworth, “to quantify production volumes, to enable us to identify the efficiency of the various facilities and predict stoppage times, and to assess WIP levels. More importantly, we could predict the accuracy of achieving the most efficient sequencing of the three models down the two lines.”

Objectives

Although achieving the volumes demanded by the business plan was, commonly, not a concern with the Body Shop, Paint Shop and Trim Shop, all presented individual challenges which Nissan used the WITNESS model to address. In the Body Shop the objective was to maintain the correct sequences at the merge-points with the engine compartment and manual assembly (mainly for the Micra) lines, and to clearly identify possible bottlenecks. These could, for example, be caused by the longer assemble cycle times involved in the Almera build, or certain sequences falling ‘out of synch’ to impair throughout.

In the Paint Shop Nissan had to look at the questions of quality control reject rates after touch-up, and the timely delivery of the jigs to carry individual vehicle panels through the process. Again sequencing was critical, to sustain efficient flow through the ovens. Sequencing logic was vital in Trim Shop too, simulating the douki seisan - “ideal manufacturing system” - concept recently adopted in Nissan plants worldwide.


Results

WITNESS has played a substantial role in enabling Nissan gear up for, and sustain, the successful production of three models on two assembly lines. For the Body Shop operations it has enabled Nissan to assess the impact of schedule mix and loss of sequence, and to devise action plans to handle breakdowns. In the Paint Shop ‘first time OK’ rates have risen to minimise disruptions and, again, the capacity to accommodate and resolve breakdowns has been improved. Recirculation levels in the Trim Shop have been cut and the levels of vehicles held has been reduced.

Says Paul Wreglesworth: 

“The douki seisan concept aims to reduce lead-time throughout the entire supply chain, from customer order to delivery of the finished vehicle. By accurately predicting the time and sequence in which vehicles are built, order lead times, finished vehicle stocks, inventory and distribution costs will all be reduced. Adding a third model to the two existing lines at Sunderland has significantly increased the process complexity and necessitated a radical new ‘time and sequence’ system. WITNESS has been invaluable in enabling us to understand the scheduling, and try a range of ‘what-if’ scenarios, in the light of an enormous number of variable, to ensure we got it right.

“WITNESS is continuing to help the company’s engineers monitor and fine-tune operations and since the introduction of the new system, production volumes of all three vehicles has gone up.”


Loading blog comments..

Post a Comment

Thank you, your comment is awating approval
Submit